ICAP/FCM Market NoticesICAP/FCM Market Notices2025 Final Annual Peak Load2026-04-20T22:39:13Z2026-04-20T22:39:13Z<strong>When:</strong> Monday April 20, 2026 2:33 PM<br/><p>黑料网 released the Forward Capacity Market, Market Information Server (MIS) report entitled Special Annual Peak Load (SP_FCMANNUALPEAK) today, April 20, 2026.</p>
<p>The 2025 final annual peak load information has been included in the "黑料网 Annual System Peak Day, Hour & Load MW" spreadsheet. This spreadsheet is located <a href="http://www.iso-ne.com/isoexpress/web/reports/auctions/-/tree/ann-sys-peak-day-hr-load">here</a>. </p>2026-04-20T22:39:13ZForward Capacity Market Capacity Supply Obligation Bilateral Period for June 2026 Results Available2026-04-17T20:29:34Z2026-04-17T20:29:34Z<strong>When:</strong> Friday April 17, 2026 12:28 PM<br/><p>The <a href="/markets-operations/markets/forward-capacity-market/fcm-auction-bilateral-results-cp?cp=1445">Forward Capacity Market Capacity Supply Obligation Bilateral Period</a> for June 2026 results have been approved. Updated Capacity Supply Obligation positions resulting from the Capacity Supply Obligation Bilateral Period can be found in the Forward Capacity Tracking System application under Commitment Period 2026-2027.</p>2026-04-17T20:29:34ZNew Capacity Show of Interest Forms for the 2026 Interim Reconfiguration Auction Qualification Process due by April 30, 2026.2026-04-16T16:41:17Z2026-04-16T16:41:17Z<strong>When:</strong> Thursday April 16, 2026 8:40 AM<br/><p>The New Capacity Show of Interest Form submittal window for the 2026 interim reconfiguration auction qualification process is open and will close on April 30, 2026 at 23:59. These Show of Interest Forms must be submitted via the Forward Capacity Tracking System.<br />
<br />
Materials detailing the Show of Interest Form requirements and submission process for the 2026 interim reconfiguration auction qualification process can be found on the ISO-NE Forward Capacity Market Participation Guide webpage: <a href="/markets-operations/markets/forward-capacity-market/fcm-participation-guide/interim-reconfiguration-auction-qualification" target="_blank">/markets-operations/markets/forward-capacity-market/fcm-participation-guide/interim-reconfiguration-auction-qualification</a><br />
<br />
Contact Participant Support at (413) 540-4220 or <a href="mailto:askiso@iso-ne.com" target="_blank">askiso@iso-ne.com</a><mailto:<a href="mailto:askiso@iso-ne.com" target="_blank">askiso@iso-ne.com</a>> or via an Ask ISO Case for any questions.</p>2026-04-16T16:41:17ZCalculation of Qualified Capacity for the Forward Capacity Market Monthly Capacity Supply Obligation Bilateral Window for June 20262026-04-09T21:02:05Z2026-04-09T21:02:05Z<strong>When:</strong> Thursday April 9, 2026 12:43 PM<br/><p>In accordance with Market Rule 1 Section III.13, the updated Qualified Capacity for each Resource for June 2026 is available for viewing in the Forward Capacity Tracking System (FCTS) under the Resource Position Summary. The amount of capacity that each Resource may transfer or acquire in the Forward Capacity Market Capacity Supply Obligation Bilateral Window for June 2026 is available for viewing in the Forward Capacity Market CSO Bilateral Contract Management UI under the terms Max Transferring Capacity and Max Acquiring Capacity.</p>2026-04-09T21:02:05ZFailure to Cover Charge Rate for Capacity Commitment Period 2026-2027 now available2026-04-02T17:20:24Z2026-04-02T17:20:24Z<strong>When:</strong> Thursday April 2, 2026 9:11 AM<br/><p>The Failure to Cover Charge Rate for Capacity Commitment Period 2026-2027 has been approved. The results summary can be found <a href="/markets-operations/markets/forward-capacity-market/">here</a></p>2026-04-02T17:20:24ZThe Q1 2026 Critical Path Schedule (CPS) update for non-commercial resources is now due2026-04-01T17:29:52Z2026-04-01T17:29:52Z<strong>When:</strong> Wednesday April 1, 2026 9:26 AM<br/><p>Pursuant to the 黑料网. Transmission, Markets, and Services Tariff Section III.13.3, the Q1 2026 CPS update is now due for those non-commercial resources that either cleared in a Forward Capacity Auction or requested monitoring of their CPS. Please submit the update under the Monitored CPS tab in the Forward Capacity Tracking System (FCTS) for all applicable Capacity Commitment Periods as appropriate. The update should be submitted by the end of Wednesday, April 8, 2026 (by 23:59).</p>
<p>Pursuant to Section III.13.3.2.2 of the 黑料网. Transmission, Markets, and Services Tariff, "for each critical path schedule milestone achieved since the submission of the previous critical path schedule report, the Project Sponsor must include in the critical path schedule report documentation demonstrating that the milestone has been achieved by the date indicated." This section of the 黑料网. Transmission, Markets, and Services Tariff also provides detailed examples of the type of documentation that can be included to demonstrate completion of each milestone.</p>
<p>Review the <a href="/static-assets/documents/2019/04/cps_monitoring.htm">Critical Path Schedule Report Training presentation here</a> for guidance on submitting the CPS report in FCTS.</p>
<p>If you experience any technical issues while submitting the report or if you have any questions regarding this message, please contact the Participant Support and Solutions Team by submitting a case via <a href="https://askiso.iso-ne.com/s/contactsupport" target="_blank">Ask ISO</a>, emailing <a href="mailto:AskISO@iso-ne.com" target="_blank">AskISO@iso-ne.com</a>, or by phone at (413) 540-4220.</p>2026-04-01T17:29:52ZForward Capacity Market Third Annual Reconfiguration Auction (w/ ARTs) Results Available for Capacity Commitment Period 2026-20272026-03-31T23:12:27Z2026-03-31T23:12:27Z<strong>When:</strong> Tuesday March 31, 2026 3:09 PM<br/><p>The Forward Capacity Market Third Annual Reconfiguration Auction and Annual Reconfiguration Transaction for Capacity Commitment Period 2026-2027 results have been approved. Updated Capacity Supply Obligation positions resulting from the auction approval can be found in the Forward Capacity Tracking System application under Commitment Period 2026-2027. Updated Annual Reconfiguration Transaction status can be found in the Forward Capacity Market Reconfiguration Auction & ARTs application under Commitment Period 2026-2027. Individual MIS reports can be found in the MIS reports titled SP_ARARESULT. The results summary for this auction can be found <a href="/markets-operations/markets/forward-capacity-market/fcm-auction-bilateral-results-cp?cp=1445">here</a>.</p>2026-03-31T23:12:27ZForward Capacity Market Capacity Supply Obligation Bilateral Period and Monthly Reconfiguration Auction for June 2026 to Open2026-03-26T18:52:30Z2026-03-26T18:52:30Z<strong>When:</strong> Thursday March 26, 2026 10:48 AM<br/><p>In accordance with Market Rule 1, Sections III.13.4 and III.13.5, the submission period for submitting Capacity Supply Obligation Bilateral Contracts to the Forward Capacity Market CSO Bilateral Period for June 2026 will open on April 10, 2026 (00:00) and will close on April 13, 2026 (11:00). The submission period for submitting bids and offers to the Forward Capacity Market Monthly Reconfiguration Auction for June 2026 will open on April 22, 2026 (00:00) and will close on April 23, 2026 (11:00).</p>2026-03-26T18:52:30ZForward Capacity Market May 2026 Reconfiguration Auction Results Available2026-03-25T16:44:37Z2026-03-25T16:44:37Z<strong>When:</strong> Wednesday March 25, 2026 8:42 AM<br/><p>The Forward Capacity Market May 2026 Reconfiguration Auction results have been approved. Updated Capacity Supply Obligation positions resulting from the auction approval can be found in the Forward Capacity Tracking System application under Commitment Period 2025-2026. Individual MIS reports can be found in the MIS reports titled SP_MRARESULT. The results summary for this auction can be found <a href="/markets-operations/markets/forward-capacity-market/fcm-auction-bilateral-results-cp?cp=1444">here</a>.</p>2026-03-25T16:44:37ZBid/Offer Limits Available for the Forward Capacity Market May 2026 Reconfiguration Auction2026-03-18T20:29:04Z2026-03-18T20:29:04Z<strong>When:</strong> Wednesday March 18, 2026 12:28 PM<br/><p>In accordance with Market Rule 1 section III.13.4.2, the amount of capacity that each Resource may bid or offer into the Forward Capacity Market May 2026 Reconfiguration Auction is available for viewing in the Forward Capacity Market Reconfiguration Auction UI under the terms Max Demand Bid MW and Max Supply Offer MW.</p>